S7-400
How can the S7-400H work in the event of a failure?
How can the S7-400H work in the event of a failure?
How can the S7-400H work in the event of a failure?
S7-400H works on the principle of active surplus. He is on standby in the event of a failure, and takes control of the subunits. It automatically becomes the main unit in case of failure.
You know a better answer?
The question about Siemens S7-400 has already been answered, but there may be a better solution or alternative available by now. If you know it, answer the question now and increase your reputation as an industry expert in our B2B community.
What are the upgrade options from S7-400 PLC ?
<1Kviews
We currently have an S7-400 PLC installed in our plant since 2013. There is a push to now upgrade this system, but it is still...
Was the content helpful to you?