Pure Charging StationWebasto
Pure Charging Station
2.1K views

How to get 11Kw from the charger?

I can only get 8Kw from the charger

Answers

Top answer

You can use the DIP switches inside the unit to set whether it runs 1-phase or 3-phase and whether it charges at 16A or 32A.
DIP switch position bottom = 0, top = function

  • DIP switch 1: 0 = 1-phase (230V), function = 3-phase (400V)
  • DIP switch 2: 0 = 16A (per conductor), function = 32A (per conductor)

-> DIP switch 1: = 0, DIP switch 2: =0=> 3.6kW
-> DIP switch 1: = function, DIP switch 2: = 0=> 11kW
-> DIP switch 1: = function, DIP switch 2: = function=> 22kW


Webasto Pure.PNG

[Source](https://www.energieloesung.de/media/pdf/1d/24/ef/Webasto-Pure-Einbauanweisung.pdf)

fbrgstllr
fbrgstllr / skilled (642)
 

You know a better answer?

The question about Webasto Pure Charging Station has already been answered, but there may be a better solution or alternative available by now. If you know it, answer the question now and increase your reputation as an industry expert in our B2B community.

Related Questions Related Questions

Receive Important Update Messages Stay up to date on Webasto Pure Charging Station

Was the content helpful to you?

Advertisement Advertise here?
Udemy IT certification ad